Typical jobs

Six jobs, described the way they are actually run.

These are representative scopes, not case studies. Rather than borrow somebody else’s photographs, each job below is set out in the detail a quotation would use: what is typically involved, when the work happens, how long it takes and what is handed over at the end.

Every figure on this page is typical or approximate, because that is what it is. Nothing here refers to a job already delivered, and no client, address or date appears on it. As real jobs are completed, their photographs and their real numbers take the place of the drawings below.

works areaopen to traffictouch-dry in roughly 20 to 30 minutes in suitable conditions
Typical size
Approximately 80 to 120 bays, plus aisles, arrows and crossings
When the work happens
One night, from close of trade to the first morning delivery
Typical time on site
Six to nine hours, of which roughly two are preparation
Trafficable
Waterborne acrylic is touch-dry in about 20 to 30 minutes in suitable conditions
Handed over
Principal dimensions, the document they were taken from, before and after photographs

RETAIL STRIP / OVERNIGHT

Typical scope

A shopping centre car park re-marked between closing and opening

A worn retail car park brought back to its approved layout in a single night, so the site loses no trading time and the bays are drivable before the first staff car arrives.

On an established retail strip the layout is almost always already approved. The job is maintenance, not redesign. The set-out is taken from the layout approved for the site, the bay count does not change, and nothing is moved because it would be tidier somewhere else. Where a measured dimension appears not to meet the applicable requirement, it is raised in writing before the night rather than repeated in fresh paint.

The night runs in a fixed order. The surface is swept, blown down, washed where it needs it and lightly scraped. The set-out is chalked from the measured baseline and checked against the plan. Only then is the machine started. Work begins at the end of the car park that has to carry the earliest morning traffic, so the section with the least drying time available is the section that gets the most of it.

Marking is weather dependent and a retail night is no exception. If the surface is wet, damp or too cold when we arrive, the visit is rescheduled rather than painted over, at no penalty to either party. That is stated in the quotation, because a car park marked on a bad night costs more to fix than the night was worth.

The service behind this job: Car park re-marking

aislewalkwaydrop zonehazard hatchingmarked to the site traffic management plan
Typical size
Approximately 1,500 to 4,000 square metres of floor, marked in sections
When the work happens
Between shifts, across a weekend, or section by section during operating hours
Typical time on site
One to three visits depending on how much of the floor can be cleared at once
What is marked
Aisle lines, walkways, crossings, racking and pallet zones, hazard delineation
Handed over
A marked-up copy of the plan the set-out was taken from, plus photographs

WAREHOUSE / OPERATING FLOOR

Typical scope

A warehouse floor marked around a working shift

Aisles, pedestrian walkways, crossing points, racking lines and hazard hatching set out to the site traffic management plan and marked in sections, so the floor keeps operating while the work proceeds.

A point worth making before the quotation rather than after it: painted lines are an administrative control, not a physical one. WorkSafe Victoria reports that forklifts cause more workplace deaths and injuries than any other piece of equipment, and that more than half of forklift-related fatalities have involved pedestrians. Marking makes the traffic management plan visible on the floor and defines the zone a barrier enforces. It does not stop a forklift, and it is not sold here as though it does.

The work is set out to the traffic management plan supplied by the site. We do not write traffic management plans and we do not carry out risk assessments. Where the plan and the floor disagree, because racking has moved or a door has been changed, that is raised in writing and the site decides, not the marker.

Floors are marked in sections so the operation continues. A section is cleared, swept, degreased where forklift traffic has left a film, chalked, checked and marked, then released before the next section is cleared. A previously sealed or heavily contaminated slab will not hold paint for long, and where that is the condition of the floor it is recorded in writing before anything is applied rather than discovered a season later.

The service behind this job: Warehouse and factory floor marking

2.4 m bay2.4 m shared5.4 mpathAS/NZS 2890.6:2009 · AS 1428.1:2021
Typical size
Approximately two to eight accessible bays and their shared areas
When the work happens
Outside trading hours, or in a half-day where the bays can be closed off
Typical time on site
Three to six hours, including the measuring
Documents used
The approved plans, AS/NZS 2890.6:2009, AS 1428.1:2021, NCC Volume One Part D4
Handed over
The measured dimensions of each bay and shared area, with the document each was checked against

ACCESSIBLE PARKING / AS 2890.6

Typical scope

Accessible bays and shared areas set out to AS/NZS 2890.6

Yellow delineation, the shared area and the symbol of access reinstated on bays that have worn to the point where the bay no longer works for the person it was built for.

Three faults recur on existing sites, and almost never through anyone’s negligence. Bays delineated in white rather than yellow. Shared areas whose hatching has worn away, so drivers now park in them and the bay stops functioning even though the bay itself is untouched. And a blue panel with the symbol of access marked on a bay that does not have the dimensions, the shared area or the connection to an accessible path to support it.

The edition applied is the one the instruments binding the site actually cite, not automatically the newest published. At present Clause 52.06-5 of the Victoria Planning Provisions and the National Construction Code both name AS/NZS 2890.6-2009. Where a building surveyor or an access consultant directs that a later edition applies, we work to it and record that direction in the quotation.

Where a bay cannot be made to meet the applicable requirement by re-marking alone, because the geometry or the path of travel will not allow it, that is stated in writing and the bay is not simply repainted to look resolved. Kontur Line Marking is a marking contractor. It does not certify compliance, and the number of accessible spaces a building requires is a matter for NCC Volume One Part D4 and the relevant building surveyor.

The service behind this job: Accessible parking bays and shared areas

chalk the set-out,check it againstthe plan, then paintapproved plan2.62.62.62.62.62.6 m4.9 m
Typical size
Approximately 40 to 150 bays on a newly sealed or poured surface
When the work happens
After the seal has cured, and before practical completion
Typical time on site
One to two days, with roughly half of it spent measuring and checking
Sequence
Measure, chalk, check against the plan, then paint. Never the other order
Handed over
Principal dimensions and the plan revision they were taken from

NEW BUILD / OCCUPANCY DATE

Typical scope

A new set-out from approved plans, worked back from an occupancy date

A bare sealed surface measured, chalked, checked against the approved plans and then marked, scheduled around the trades that finish before it and the date the building has to open.

For a builder, marking sits on the critical path rather than at the end of it. Under the planning provisions a car park must be constructed in accordance with the approved plans before a new use commences or new buildings are occupied, so a car park that is poured, sealed and unmarked can hold up an opening for reasons that have nothing to do with the building.

The layout is established from the approved plans, chalked on the surface, and checked against the plan before the machine is started. Where the plan itself appears to conflict with Clause 52.06-9 Table 2 of the Victoria Planning Provisions, or with AS/NZS 2890.1:2004 or AS/NZS 2890.6:2009 where those apply, the conflict is raised in writing and we wait for a direction. A plan conflict is not resolved unilaterally on site, however obvious the answer looks at the time.

New asphalt needs to cure before it will hold marking, and the time it needs depends on the mix, the depth and the weather. Where the seal is not ready, moving the marking date is cheaper than marking twice, and that is said plainly at the time rather than absorbed quietly into a program that was already tight.

The service behind this job: New car park set-out

2.6 m4.9 m6.4 mClause 52.06-9 Table 2 · AS/NZS 2890.6
Typical size
Approximately 30 to 70 bays, plus a drop-off zone and pedestrian routes
When the work happens
Weekend, term break or pupil-free day. Not during operating hours
Provided before attendance
Working with Children Check, certificate of currency, safe work method statement
Typical time on site
One day, or one night where the site allows it
Handed over
Dimensions, the source document, and before and after photographs

SCHOOL / OUTSIDE HOURS

Typical scope

A school or childcare car park marked outside operating hours

Staff parking, the drop-off zone and the pedestrian route between them, marked during a term break or on a weekend, with a current Working with Children Check provided before attendance.

Schools and childcare centres set their own conditions for contractors on site and those conditions are not negotiated down. A current Working with Children Check is provided before attendance, sign-in is followed as the site requires it, and the work is scheduled outside operating hours as a matter of course rather than as an accommodation asked for in advance.

The pedestrian route is the part of this job that matters most and it is the part most often marked badly. A walkway that stops at the point it becomes useful, at the kerb, at the gate, or where the cars actually cross it, is worse than no walkway, because it hands the pedestrian back to the driver at the moment the driver is least able to predict them. Routes are marked continuously, including the awkward sections, and crossing points are marked where people already cross.

Where a school wants the layout changed rather than restored, that is a different question. Altering an approved layout or the number of spaces engages Clause 52.06 of the planning scheme and needs plans prepared to the satisfaction of the responsible authority. We will quote the marking once the revised approved plans exist. We do not design drop-off arrangements and we do not write the school’s traffic management.

The service behind this job: Pedestrian walkways, crossings and hatched zones

2.6 m4.9 m6.4 mClause 52.06-9 Table 2 · AS/NZS 2890.6
Typical size
Approximately 50 to 100 bays, split into two stages
When the work happens
Two consecutive nights, or two Sundays
Typical time on site
Four to seven hours per stage
During the work
One half coned and signed off at a time. The other half stays open
Handed over
Dimensions, the source document, and photographs of each stage

MEDICAL CENTRE / STAGED

Typical scope

A medical centre or dealership marked in halves, so parking is never fully lost

The car park split into two stages over two visits, with one half coned and signed at a time, so patients keep a bay and a dealership keeps its stock where it stands.

Some sites cannot close. A medical centre cannot tell tomorrow’s patients to park somewhere else, and a dealership cannot move a yard of stock off site for a night at a sensible cost. Staging the work in halves costs a second mobilisation of time. It does not cost a trading day, and on those two site types that trade is usually the right one.

The joint between the two stages is where staged work goes wrong, so it is set out first. The measured baseline is established once, on the first visit, and carried across the stage boundary rather than re-established on the second night by eye. Lines that cross the boundary, aisle edges, walkways and hatching, are chalked on the first visit even where they will not be painted until the second, so the two halves meet as one layout instead of two.

The honest cost of staging is that it doubles the number of weather-dependent nights. If the second night is rained out the site runs on one fresh half and one worn half until we return, which is usually within the week. That is said before the quotation is accepted, not after the second night is lost.